Resident Landscape Architect Weekly Report 16th to 22nd July 2013

Written by

in

weekly report 160713 1

Irrigation trenching along the Spine

This week saw the continuation of trenching for the irrigation and the first pipes being laid. We have been discussing looking further at the flora in the hills directly around the school and the possibility of removing some plants and seeing whether they will transplant successfully during these summer months.

weekly report 160713 2

The laying of the first mainline pipes for the irrigation system